Bitfarms is ending its expansion in Paraguay to focus on North American energy and digital infrastructure for high-performance computing and artificial intelligence. The company entered a definitive share purchase agreement to sell its 70 MW Paso Pe site in Paraguay to Sympatheia Power Funds for up to $30 million. This exit follows the $85 million sale of the Yguazu facility to HIVE Digital Technologies. Under the Paso Pe terms, the buyer will pay $9 million in the first quarter of 2026, which includes a $1 million non-refundable deposit already paid by the buyer. The company expects to receive an additional $21 million in payments over the ten months following the close of the deal. Ben Gagnon, the Bitfarms CEO, intends to use these funds to reinvest in the company’s North American energy infrastructure in 2026. This strategic shift rebalances the company energy portfolio to 100% North American assets. You should observe how these funds move into the company’s 1 GW growth pipeline in the United States. The company will narrow its focus to the Panther Creek and Scrubgrass sites in Pennsylvania. This decision follows a $46 million loss in the third quarter, which was nearly double the $24 million loss from the same period last year. The company will wind down Bitcoin operations over 2026 and 2027.
| Asset/Metric | Detail |
|---|---|
| Paso Pe Sale Price | Up to $30 million |
| Yguazu Sale Price | Approximately $85 million |
| Paso Pe Closing Payment | $9 million in Q1 2026 |
| Paso Pe Milestone Payments | Up to $21 million over 10 months |
| Yguazu Payment Structure | $25m at close, $31m over 6 months, $19m power deposit, $10m capital |
HIVE scales its Paraguayan footprint
HIVE Digital Technologies maintains its momentum in the Paraguayan market after it acquired the Yguazu assets from Bitfarms. The company completed the second phase of its Yguazu facility in Valenzuela in September 2025, which brought the site to its full 200 megawatt capacity. This operation currently mines more than 8 Bitcoin every day. HIVE has grown its global hashrate to over 18 EH/s. The company acquired the Yguazu site in January 2025 for $56 million. This acquisition follows the completion of the first 100 MW phase. In April 2025, the company produced 102 Bitcoin, which averaged 3.4 Bitcoin per day or 15.8 Bitcoin per exahash. The fleet efficiency for that month was 20.7 joules per terahash. HIVE has reached a peak hashrate of 6.6 EH/s and an average monthly hashrate of 6.5 EH/s. The company expects to add 6.5 EH/s of capacity through its Phase 2 expansion using Bitmain S21+ Hydro ASICs. To achieve this, over 13,400 hydro-cooled units have already shipped. HIVE is also preparing its Valenzuela site for an additional 100 MW of air-cooled containers. This expansion should allow the company to surpass 25 EH/s globally. The company used the redeployment of 30 MW of BUZZ Miners to save $27 million in capital expenditure.
Regulatory and energy hurdles in Paraguay
Regulatory changes in Paraguay create significant economic pressure for Bitcoin mining companies. The National Power Administration (ANDE) increased energy fees for miners by up to 16% depending on power expenditure. This increase led nine mining clients to cancel their contracts because they refused to continue with the activity after being regularized to the new category. Authorities also monitor unauthorized mining operations that use the power grid illegally. The Paraguayan government classifies Bitcoin mining as an industrial activity under the Ministry of Industry and Commerce. This classification means that financial authorities and the central bank do not oversee the industry. Juanjo Benitez Rickmann, a Paraguayan mining firm managing director, argues that a clear framework is necessary to attract $30 million investments rather than $1 million investments. Fernando Arriola Arza, a Paraguayan mining liaison, notes that the country has a significant criminal presence that requires legal protection for business owners. While the Itaipu Dam provides 5.5 gigawatts of surplus energy, the sudden fee hikes and licensing requirements create new obstacles. The Itaipu Dam produced 37,270 GWh in the first half of 2025 alone, which is almost three times the country’s domestic needs. Will the regulatory pressure in Paraguay eventually force more large-scale miners to flee toward North American grids?
Strengthening the North American base
Bitfarms is expanding its footprint in the United States to secure more stable energy and more favorable trading options. The company is developing a 120 MW site in Sharon, Pennsylvania, which connects to the Pennsylvania-New Jersey-Maryland Interconnection. This site has the capacity to support 8 EH/s of hashrate. Bitfarms currently maintains 341 MW of energized capacity in North America and has 430 MW under active development. The company also owns coal-fire power plants and data center infrastructure from its acquisition of Stronghold Digital in March 2024. The Sharon deal involves a five-year lease for an 11,200 square foot warehouse. The company expects to bring 12 MW online in the fourth quarter of 2024 and the remaining load in the second half of 2025. The transaction involves the issuance of 1.53 million shares worth approximately $3.6 million, which implies a cost of about $300,000 per megawatt for the existing 12 megawatts of capacity. This expansion follows the termination of a lease by Mawson Infrastructure in the same area in February 2024. The company’s total multi-year pipeline stands at 2.1 gigawatts, with roughly 90% located in the United States.